Chris Woods and Chelsea Riddle describe ground improvement for a one-million-square-foot warehouse built on a former strip-mining site in northeastern Pennsylvania. The site contained deep, highly variable mine spoil, wet and moisture-sensitive soils, substantial cuts and fills, and abandoned underground mines. After heavy rainfall and test pits revealed soft, silty areas unsuitable for dynamic compaction, the original plan was expanded to include aggregate piers, settlement monitoring, and mine grouting.<br /><br />Dynamic compaction improved the upper soil crust, achieving average post-treatment resistance above 25 blows per foot in the upper 25 feet. Aggregate piers treated two critical areas: one to limit settlement and match the response of compacted ground, and another to reinforce and drain fill beneath a thick embankment. Settlement monitoring showed about 1.5–2 inches of settlement, leveling off after 90 days. Investigation found most mine roofs had collapsed, limiting the need for grout. The presenters emphasize thorough geotechnical assessment, collaboration, adaptable solutions, and stable working platforms.
Keywords
ground improvement
dynamic compaction
aggregate piers
mine grouting
settlement monitoring
×
Please select your language
1
English