Ground Stabilization using Deep Soil Mixing Techni ...
Paper
Paper
Back to course
Pdf Summary
The project required a 120 m-long railway approach ramp to rise approximately 6 m and connect a new ground-level line to an existing elevated metro line. The reinforced-concrete box structure imposed ground pressures of 75–280 kPa. Because the existing embankment fill was relatively compressible, untreated settlements were estimated at about 50 mm—above the project limit of 20 mm, including a maximum of 10 mm after track installation.<br /><br />Deep Soil Mixing (DSM) was selected instead of piled foundations as a cost-effective, low-vibration ground improvement solution. Designed in accordance with the Federal Highway Administration’s 2013 guidance, the scheme used 2.0 m-diameter cement-mixed columns in a grid beneath the structures. The columns had a target unconfined compressive strength of 0.75 MPa and were spaced 2–4 m apart according to loading requirements. The design accounted for column crushing and used area replacement ratios to meet settlement and capacity criteria.<br /><br />A 0.5 m-thick granular load transfer platform (LTP), reinforced with two layers of biaxial geogrid, was installed above the treated ground to distribute structural loads evenly. Quality verification included column coring and strength testing, plate-load testing of the LTP, and a zone load test on four trial columns. Under a maximum test pressure of 250 kPa, the trial section recorded an average settlement of 16 mm.<br /><br />The trial results supported the selected DSM-and-LTP system as a means of carrying the specified loads while controlling settlement to the project requirements.
Keywords
Deep Soil Mixing
DSM
railway approach ramp
settlement control
ground improvement
load transfer platform
geogrid reinforcement
cement-mixed columns
elevated metro line
foundation design
×
Please select your language
1
English