Progress on the $750M lock project on the Monongahela River was derailed by discovery of large anomalies in the 6.5-7-ft dia. drilled shafts of the new river wall foundation. The anomalies were located 45 to 50' below the top of the wall at the critical shaft-to-wall interface, and ranged in thickness from several inches to 2-plus feet. A Specialty team, comprised of representatives from the contractor, the Government, and structural design consultants, was formed to evaluate the extent of the problem and the impact on the new lock wall. With no standard method in place, the Government took the lead to develop acceptance criteria for the repairs while the contractor took the lead to identify the repair means and methods. The Government developed a detailed Quality Control plan to capture and document all of the repair data and to approve each shaft repair in a timely manner. This paper provides an overview of the anomalies encountered and the need for repairs; discusses the details of the repair plan; and provides details on the unique quality control measures employed to verify the repairs. By developing and adhering to a detailed quality control plan, the structural integrity of all of the shafts was successfully restored.
Subjects: specification, risk, constructability, schedule, Observational Method, shoring, excavation
Author: Alex J. Bredikhin, P.E., District Risk Manager for Mega-projects
Publisher: DFI