An access pathway and working platform were designed and constructed for equipment access for a Deep Soil Mixing (DSM) pilot study over a coal combustion residual (CCR) surface impoundment (SI). The DSM pilot study was conducted to evaluate slurry mix designs and construction techniques for installing DSM columns up to 95 feet deep. Two-dimensional (2-D) limit equilibrium and 2-D finite element analyses were used to evaluate multiple failure mechanisms including: (i) bearing capacity, (ii) punching shear of mixed ground and underlying CCR, (iii) effect of fluidized DSM columns on working platform stability, and (iv) liquefaction. The analysis results were used to design ground improvement required to increase bearing capacity and stability of the CCR under the proposed equipment access route. A long-reach
excavator was used to perform shallow bucket mixing and walk onto the CCR SI atop previously mixed cells following a minimum cure time and acceptance of quality control test results. Prior to mobilizing the DSM rig, a static load test was conducted to evaluate performance of the working platform. Both the access pathway and working platform demonstrated acceptable performance under the design loads during the DSM pilot study. This case study emphasizes the economic and safety benefits that can be realized by appropriately designing critical temporary work items such as access pathways and working platforms in difficult ground conditions.
Subjects: working platform, CCR, ground improvement, soil mixing, finite element
Author: Daniel J. Woeste, P.E., William Tanner, P.E., Juan M. Pestana, Sc.D., P.E., Paul J. Sabatini, Ph.D., P.E., D.GE, Jeremy M. Gasser, P.E. and Cuneyt Gokmen, P.E.