A test pile program was undertaken at a project site in Ain Sukhna, Egypt for an import/export oil jetty. Two 1219 mm diameter open ended steel pipe piles were evaluated at two separate test locations. Each test pile was dynamically tested during initial drive utilizing a Pile Driving Analyzer (PDA). Restrike testing was also performed to evaluate the time dependent soil setup. One static compression test and one static tension test was performed at each test location. A correlation of the static and dynamic load test results was established to develop a driving criteria for the piling across the two kilometer project. The constructability benefits of shorter piles will be discussed in more detail, given that the pile lengths were shortened by 9 to 10 meters on average. Lastly, the use of a four pile linear layout to perform both compression and tension tests will be covered.
Subjects: Pile Driving Analyzer (PDA), Static Load Testing (SLT), Soil Set-up, Pipe Piles
Author: Brandon Phetteplace, P.E., Tom Hyatt, P.E. and Camilo Alvarez, P.E.