110 N. Carpenter is new commercial building located in the West Loop neighborhood of Chicago, Illinois. The new home to the McDonalds Corporation work headquarters, accelerated project delivery methods were essential to meet the scheduling demands for this project along with other projects slated to start in the region. As such top-down construction methods were utilized to allow for above and below grade construction to proceed in parallel in lieu of more conventional bottom-up construction methods, thus
compressing the project schedule. To achieve this plan, perimeter secant pile walls were constructed in conjunction with interior columns/drilled shafts and a shear wall core constructed from inside a temporary cofferdam. The use of secant pile walls allowed for efficient accommodation of a variety of loading conditions including: exterior curtain walls loads, perimeter column loads, tower crane foundation loads, and in-plane shear loads. Furthermore, this system allowed for efficient and fluid operation of equipment on site in order to accommodate the 90-day window allotted for initial foundation construction.
Subjects: secant, top-down construction
Author: Dave R. Sutfin, P.E., S.E. and Joe Lodde